Please E-mail suggested additions, comments and/or corrections to Kent@MoreLaw.Com.

Help support the publication of case reports on MoreLaw

R.M. Packer Co., Inc. v. Marmik, LLC

Date: 11-30-2015

Case Number: 14-P-1638

Judge: Gary A. Nickerson

Court: Massachusetts Supreme Court

Plaintiff's Attorney: John Curran

Defendant's Attorney: Marilyn Vukota

Description:
At issue is whether R.M. Packer Co. (Packer) was properly found liable for attorney's fees and costs

under G. L. c. 21E, § 4A(f), after it unsuccessfully sought contribution from the defendants for costs to clean up an oil spill. In three circumstances, the statute requires that reasonable attorney's fees and costs be awarded against a plaintiff who has sued seeking contribution for environmental clean-up costs. Those three circumstances are "[i]f the court finds that (1) the plaintiff did not participate in negotiations or dispute resolution in good faith; (2) the plaintiff had no reasonable basis for asserting that the defendant was liable, or (3) the plaintiff's position with respect to the amount of the defendant's liability pursuant to the provisions of this chapter was unreasonable." Here, after a bench trial, a judge found that Packer had no reasonable basis for asserting its claim against the defendant Dockside at the time it filed suit, and accordingly awarded fees and costs under § 4A(f)(2). The judge reached this conclusion despite the fact that, before Packer filed its complaint, the Department of Environmental Protection (DEP) had issued a notice of responsibility to Dockside, stating that it had reason to believe that Dockside was a "[p]otentially [r]esponsible [p]erson."





Packer argues that DEP's position vis à vis Dockside's

potential responsibility provided a reasonable basis upon which



3

Packer could sue Dockside for contribution. Hence, Packer

argues, the judge erred in awarding fees and costs under

§ 4A(f)(2). We do not need to reach this issue because, on the

facts found by the judge (and not challenged on appeal), the

award was independently proper under § 4A(f)(3). We accordingly

affirm the award on that basis.



Background.2



Packer was in the business of selling and

delivering petroleum-based products on Martha's Vineyard.3

Before the events at issue in this case, Packer had owned a

piece of commercial property located at 27 Lake Avenue in Oak

Bluffs, where a gas station was located. In 1998, Packer



2 The facts are drawn from the trial judge's clear and detailed written findings. Where, as here, a judge acts as the trier of fact, his or her factual findings must be accepted on appeal unless shown to be clearly erroneous. See Mass.R.Civ.P. 52(a), as amended, 423 Mass. 1402 (1996). Packer does not argue that any of the judge's subsidiary findings are clearly erroneous. Moreover, the findings are in essence unreviewable because the trial transcript was not included in the appellate record. Mass.R.A.P. 16(a)(4), as amended, 367 Mass. 921 (1975), & 18(a), as amended, 425 Mass. 1602 (1997). See Kunen v. First Agric. Natl. Bank of Berkshire County, 6 Mass. App. Ct. 684, 689-691 (1978); Cameron v. Carelli, 39 Mass. App. Ct. 81, 83-84 (1995); Buddy's Inc. v. Saugus, 62 Mass. App. Ct. 256, 264 (2004).



3 Ralph M. Packer, Jr. was the company's chief executive officer; Packer employees, Scott Bailey and Mark Leith, were deliverymen.



4

installed underground fuel4 storage tanks behind the station.

Tank one was for diesel fuel; tank two was for gasoline.

Two piers stretched into Oak Bluffs Harbor nearby. On one

of those piers, Dockside owned and operated pumps that dispensed

fuel to motor boats. Dockside's pumps were connected to tanks

one and two, and Dockside purchased the fuel it needed for its

operations from Packer, who delivered it to, and stored it in,

those two tanks.



In 2000, as part of a larger business deal, Packer sold the

property, including the tanks, to Marmik, LLC (Marmik), an

unrelated firm. As a result, Marmik inherited Dockside as what

the parties call a "pass-through" customer; after the

transaction, Dockside continued to purchase fuel from Packer

(paying Packer directly), and Packer continued to deliver it to

tanks one and two. However, those tanks were now owned and

maintained by Marmik,5 and Dockside paid Marmik a per gallon

handling charge for this arrangement.6



4 When we refer to "fuel" in this opinion, we do so colloquially where it makes no difference whether the substance referred to is diesel fuel or gasoline.



5 Dockside neither leased the tanks nor exercised (or assumed) exclusive or shared control of the tanks. Dockside was

not responsible for maintenance or repairs to the tanks. Further, it had no duty to monitor the fitness of the tanks.



6 Dockside also entered into an indemnification agreement with Marmik, agreeing to indemnify Marmik from "acts or



5



Marmik adapted the property to meet its business needs.

Among other changes, it added a nine-foot fence enclosing the

area where the tanks were buried. In this same area, Marmik had

installed a concrete base with layers of sand on top, which was

customized to serve as an outdoor seating area for a restaurant

on an abutting parcel. These changes to the site made it

difficult for Packer's deliverymen to use the pole method to

check the fuel levels before filling the tanks. The pole method

entails lowering a measuring pole through the direct fill cap of

the tank to measure the level of the tank's contents. The pole

method is a customary and reliable method of measuring the level

of a tank's contents and allows the deliveryman to determine how

much fuel can be added to the tank without risking a spill.

While Packer's deliverymen had on occasion used the pole

method to measure the fuel levels, they usually relied instead

on a remote electronic sensory system known as a veeder root

system (VRS), which Packer had put in place when the tanks were

added to the site. With the aid of sensors inside each tank,

the VRS measured and recorded each tank's fuel capacity on a

running tape (akin to a sales register printout); thus, the VRS

recorded the volume of fuel in a tank and its ullage, i.e., the

number of gallons that could be added. The VRS terminal was

omissions" of Dockside and its agents. This agreement, however, does not appear to be implicated here.



6

housed in a nearby convenience store and available when the

store was open for business.

On the evening of Saturday, July 7, 2007, a Dockside

employee measured the fuel in the tanks using the VRS, which

recorded fifty-four inches of diesel fuel in tank one and

eighteen inches of gasoline in tank two. In turn, according to

the parties' well-established protocol, the Dockside employee

reported the readings to Packer, stating (in inches) the height

of fuel in each tank. In addition to reporting the fuel levels,

the Dockside employee ordered gasoline (for tank two) to be

delivered as early as possible the following morning. Dockside

did not order any diesel (for tank one). On Sunday, at about

6:00 A.M., Skip Bailey, Packer's employee, accurately recorded

Dockside's fuel levels (i.e., fifty-four inches of diesel and

eighteen inches of gasoline) in a company ledger.

For reasons set out in more detail in the margin,7 Packer

was delayed in making the delivery and Dockside's owner,

Terrence McCarthy, became correspondingly agitated that Dockside

would run out of fuel.8 Ultimately, Leith made the delivery.

7 Bailey intended to deliver gasoline to Dockside after a delivery via ferry to another customer located on Chappaquiddick Island. That delivery was dependent on the tides, and Bailey was delayed on Chappaquiddick Island, due to unfavorable conditions that prevented the ferry from returning to Edgartown.

8 McCarthy left two messages with an outside answering service for Packer, indicating that without a prompt delivery



7

However, rather than delivering gasoline, he delivered diesel

fuel. Moreover, he did not check tank one's capacity, either by

the pole method or by using the VRS terminal before filling the

tank. Nor did he take any other reasonable step to ascertain

the level of diesel fuel in tank one.9 Instead, Leith attached

the truck's hose to the remote (indirect) fill spout for tank

one and proceeded to fill it. At the moment he began offloading

diesel fuel, tank one had room for about 273 gallons. By the

time Leith stopped force pumping diesel fuel, he had delivered

1,060 gallons of diesel, the tank had ruptured, the sensor rod

within the tank had shot through the top of the tank "like a

rocket," and diesel fuel was gushing from the tank "like a small

geyser." The best estimate is that 787 gallons of diesel fuel

spilled as a result.

In the aftermath of the spill, the DEP conducted an

investigation that led it to send a notice to Dockside stating

that it had reason to believe that Dockside was "a Potentially

Dockside would run out of fuel. Driving to the site, a Packer employee, Mark Leith, telephoned McCarthy, who voiced his urgent need for fuel. McCarthy did not refer to "diesel" fuel, either in his messages left with the answering service or in conversation with Leith. Nor did Leith inform McCarthy that diesel, not gasoline, would be delivered that day.

9 Leith had delivered 2,000 gallons of diesel fuel the previous day which, the trial judge found, should have raised doubts in Leith's mind that additional diesel fuel was needed. He could have easily resolved any such doubt by walking over to the Dockside pumps.



8

Responsible Party (a 'PRP') with liability under . . . G. L.

c. 21E, § 5, for response costs." A like notice was sent by DEP

to Packer, indicating that Packer was also a PRP liable under

the Act for the spill.

Packer hired an environmental firm to remediate the spill

and, all told, the clean-up costs came to $300,000, which were

assumed by Packer's insurance company. Packer then, pursuant to

G. L. c. 21E, § 4A, sent demand letters to both Dockside and

Marmik, demanding that they each contribute eighty percent of

the remediation costs (which, had the defendants acceded to the

demand, would have resulted in a significant windfall).

Packer's demand at no point changed despite the fact that, as

the trial judge found, "Packer well knew that Dockside was

blameless in this instance." The parties did not resolve their

differences and Packer brought this suit against Dockside, among

others,10 asserting liability based on common-law (negligence)

principles as well as certain provisions of G. L. c. 93A and

G. L. c. 21E, the Massachusetts Oil and Hazardous Material

Release Prevention Act (Act). Dockside asserted a counterclaim

for an award of its attorney's fees and costs under G. L.

c. 21E, § 4A(f)(1)-(3).

10 See note 1, supra; the other named defendants are not implicated in this appeal.



9

After an eight day bench trial, the judge issued findings

of fact and found in favor of Dockside on all of Packer's

claims. On Dockside's counterclaim, the judge awarded Dockside

$66,409.50 in attorney's fees and costs, relying on G. L. c. 21,

§ 4A(f)(2),11 and concluded: "[w]hen Packer filed its complaint,

application of the facts to the existing law made it reasonably

clear that Dockside was not liable under G. L. c. 21E." The

only issue before us is the award of fees and costs.12

Discussion. General Laws c. 21E is a comprehensive statute

designed to promote the prompt and efficient cleanup of sites

contaminated by the release of hazardous materials and to

provide a legal framework by which response costs are borne by,

and appropriately allocated among, those responsible. See

Commonwealth v. Boston Edison Co., 444 Mass. 324, 335 (2005);

Bank v. Thermo Elemental Inc., 451 Mass. 638, 653 (2008). Under

the Act, a person, as defined by § 2, is authorized to undertake

11 Section 4A(f)(2) authorizes an award of litigation costs and reasonable attorney's fees to a defendant if a court concludes that "the plaintiff had no reasonable basis for asserting that defendant was liable." And, in connection with his ruling, the judge cited Scott v. NG US 1, Inc., 450 Mass. 760, 773 (2008) ("the question is whether, when the complaint was filed, application of the facts to existing law made it reasonably clear that the defendant[] [was] not liable under G. L. c. 21E").

12 Although Packer's notice of appeal states that Packer appeals from the judgment, its only argument on appeal is in regards to the award of attorney's fees and costs to Dockside pursuant to G. L. c. 21E, § 4A(f)(2).



10

response actions13 to remediate a contaminated site and is

entitled to reimbursement "from any other person liable" for the

release of hazardous materials. G. L. c. 21E, § 4, third par.,

as appearing in St. 1992, c. 133, § 293. If two or more persons

are liable, then each is liable to the others for their

equitable share.14 Ibid. See Martignetti v. Haigh-Farr, Inc.,

425 Mass. 294, 308 (1997); Commonwealth v. Boston Edison Co.,

supra at 338.

Section 4A of the Act sets out a detailed prelitigation

process that a person must follow if that person wishes to

obtain contribution from others who may also have liability for

environmental clean-up costs. To begin with, the person seeking

contribution must send a demand letter specifying (among other

things) the nature, scope, and cost of the remediation, the

legal and factual basis for the demand, and the amount of

contribution or reimbursement being sought. G. L. c. 21E,

§ 4A(a). The recipient of such a demand letter is required to

13 "Response," as defined by § 2 of the Act, encompasses assessment, containment, and removal measures to remediate a site. A response action is deemed complete when it achieves a "permanent" solution, a result that is attained when a site no longer poses a "significant risk" to the public or environment for a "foreseeable period of time." G. L. c. 21E, § 3A(g), as appearing in St. 1992, c. 133, § 283.

14 There is no question in this case that Packer is liable as a "person who . . . caused or is legally responsible for a release . . . of oil . . . from a . . . site." G. L. c. 21E, § 5(a)(5), inserted by St. 1983, c. 7, § 5.



11

respond within forty-five days, and may request additional

documentation. Ibid. Either party may request that the dispute

be submitted to arbitration, mediation, or some other form of

alternative dispute resolution. G. L. c. 21E, § 4A(b). Only

after this procedure has been followed can suit be filed in

Superior Court. G. L. c. 21E, § 4A(c). The purpose of this

procedure is to prevent the parties from resorting to litigation

unless and until they have attempted to resolve the allocation

and burden of remediation among themselves.

As a further incentive to encourage the parties to take

reasonable prelitigation positions and to resolve their disputes

among themselves, the Legislature designed a fee-shifting

structure that penalizes any party who takes unreasonable

prelitigation positions regarding liability or cost sharing. A

plaintiff is to be awarded its litigation costs and reasonable

attorney's fees if the court finds that the defendant is liable

and "(1) failed without reasonable basis to make a timely

response to a [demand letter], or (2) did not participate in

negotiations or dispute resolution in good faith, or (3) failed

without reasonable basis to enter into or carry out an agreement

to perform or participate in the performance of the response

action on an equitable basis or pay its equitable share of the

costs of such response action or of other liability pursuant to

the provisions of this chapter, where its liability was



12

reasonably clear."15 G. L. c. 21E, § 4A(d). On the other hand,

"[i]f the court finds that (1) the plaintiff did not participate

in negotiations or dispute resolution in good faith; (2) the

plaintiff had no reasonable basis for asserting that the

defendant was liable, or (3) the plaintiff's position with

respect to the amount of the defendant's liability pursuant to

the provisions of this chapter was unreasonable, it shall award

litigation costs and reasonable attorneys' fees to the

defendant." G. L. c. 21E, § 4A(f). In essence, attorney's fees

and costs are to be awarded against any person who takes an

unreasonable prelitigation position regarding the existence or

extent of another person's liability.

Here, the judge awarded fees and costs, concluding that

Packer had "no reasonable basis for asserting that [Dockside]

was liable." G. L. c. 21E, § 4A(f)(2). This conclusion rested

on the judge's subsidiary findings, including his finding that

Dockside was wholly blameless for the spill in this case.

Indeed, the judge found that the spill was caused by Packer's

employee, who mistakenly delivered diesel fuel to tank one

without first measuring the level in the tank. Dockside had not

15 In the absence of one of these conditions, the plaintiff shall not receive attorney's fees and costs even if the court finds the defendant liable for contribution, reimbursement, or equitable contribution. G. L. c. 21E, § 4A(e).



13

ordered diesel fuel to be delivered and, moreover, had

accurately reported the levels in the tanks.

Although these subsidiary findings are unassailable on

appeal, they do not dispose of the question whether Packer had a

reasonable basis for asserting that Dockside was liable for

purposes of awarding attorney's fees under § 4A(f)(2).16 That

question turns on whether Packer had a reasonable basis for

asserting that Dockside fell within one of the five broadly

defined categories of persons who may be liable, under

§ 5(a)(1)-(5), "without regard to fault" or causation. G. L.

c. 21E, § 5(a), inserted by St. 1983, c. 7, § 5. If, as Packer

alleged, Dockside was strictly liable under § 5(a)(1) as an

"operator of . . . a site from . . . which there . . . has been

a release . . . of oil," Packer would have had a reasonable

basis for asserting Dockside's liability.

Whether a person is an "operator" for purposes of the Act

depends on whether the person (here, Dockside) had "actual

control of, and active involvement in, operations at the site.

16 What "ultimate legal determination" the facts support is a legal question we review de novo. Matter of Jane A., 36 Mass. App. Ct. 236, 239 (1994). See Simon v. Weymouth Agric. & Industrial Soc., 389 Mass. 146, 148-149 (1983); VMark Software, Inc. v. EMC Corp., 37 Mass. App. Ct. 610, 617 n.8 (1994) ("appellate court may reach its own ultimate conclusions based on a trial judge's findings [of fact] and may set aside a trial judge's ultimate ruling that is inconsistent with the [trial] judge's own subsidiary factual findings").



14

This is a fact-specific determination, and the appropriate

factors to consider will differ according to the nature of the

enterprise and the relation between the parties involved."

Martignetti v. Haigh-Farr, Inc., 425 Mass. at 304. The judge's

conclusion that Dockside was not an "operator" of the site

rested on the following subsidiary findings. The judge found

that Dockside did not own or control the tanks or the land in

which they sat. Nor did it have any duty to maintain the tanks.

The judge found that Dockside had no role in the day-to-day

operations of the site, and no landlord-tenant relationship

existed between it and Marmik. Dockside received no rents or

profits from the premises and was not involved in a joint

venture with Marmik. On the other hand, several of the judge's

subsidiary findings point the other way. Dockside had a long

standing arrangement (begun with Packer, and continued with

Marmik) whereby it pumped fuel from the tanks for sale to its

customers. Fuel was delivered to, and stored at, the tanks at

Dockside's instruction and for its use. Dockside's use of the

tanks was not casual or intermittent; it was pursuant to a

formalized business arrangement whereby it paid a fee to Marmik

in exchange for the use of the tanks. In addition, after

investigation, DEP notified Dockside that it (DEP) had reason to

believe Dockside was potentially liable under the Act. This

fact, taken together with those just recited, was certainly a

strong buttress for Packer's position that Dockside bore

potential liability as an operator of the site.

We need not, however, decide whether Packer had no

reasonable basis for asserting that Dockside was liable as an

operator such that an award of attorney's fees and costs was

proper under § 4A(f)(2). The award was independently proper

under § 4A(f)(3) given the judge's other findings. The judge

stated that "Packer's insistence that Dockside contribute eighty

percent of the clean up costs . . . when Packer well knew that

Dockside was blameless in this instance" was alarming.

Particularly when that demand is considered with the similar one

made to Marmik (together significantly exceeding the actual cost

of remediation), and Packer's inflexibility despite its own

responsibility for the spill, we have no difficulty concluding

that Packer's "position with respect to the amount of the

defendant's liability . . . was unreasonable" such that

attorney's fees and costs could be awarded under § 4A(f)(3).

Although in other circumstances we might not determine the

reasonableness of a presuit litigation position for the first

time on appeal, we do so here for several reasons. First, the

issue was raised and fully briefed below. Dockside's

counterclaim sought attorney's fees and costs under all three

subsections of § 4A(f), and its application for attorney's fees

also pressed all three grounds. Second, on appeal, Dockside



16

again argues that the award was proper under all three

subsections. Tellingly, Packer challenges only the award under

§ 4A(f)(2); it does not argue that the award could not rest on

§ 4A(f)(3). Finally, it is clear that the judge would have made

the award under § 4A(f)(3) as well as (or in lieu of) § 4A(f)(2)

had he considered the question. As the judge noted, had he

"reached the question of equitable apportionment of the

[response] costs vis-a-vis Dockside, a finding of zero share

would have been entered."
Outcome:
It is but a short step from this statement, considered together with the judge's subsidiary findings concerning Dockside's lack of responsibility for the spill and his forceful remarks concerning his "alarm[]" at

Parker's intransigent demand for an eighty percent contribution

to conclude that the judge would have found Packer's inflexible

contribution position unreasonable. The judgment dated September 3, 2013, and the order dated April 9, 2014, awarding attorney's fees and costs to Dockside

are affirmed under G. L. c. 21E, § 4A(f)(3).

So ordered.
Plaintiff's Experts:
Defendant's Experts:
Comments:

About This Case

What was the outcome of R.M. Packer Co., Inc. v. Marmik, LLC?

The outcome was: It is but a short step from this statement, considered together with the judge's subsidiary findings concerning Dockside's lack of responsibility for the spill and his forceful remarks concerning his "alarm[]" at Parker's intransigent demand for an eighty percent contribution to conclude that the judge would have found Packer's inflexible contribution position unreasonable. The judgment dated September 3, 2013, and the order dated April 9, 2014, awarding attorney's fees and costs to Dockside are affirmed under G. L. c. 21E, § 4A(f)(3). So ordered.

Which court heard R.M. Packer Co., Inc. v. Marmik, LLC?

This case was heard in Massachusetts Supreme Court, MA. The presiding judge was Gary A. Nickerson.

Who were the attorneys in R.M. Packer Co., Inc. v. Marmik, LLC?

Plaintiff's attorney: John Curran. Defendant's attorney: Marilyn Vukota.

When was R.M. Packer Co., Inc. v. Marmik, LLC decided?

This case was decided on November 30, 2015.