Willow Glen Trestle Conservancy v. City of San Jose

Date: 05-21-2020

Case Number: H047068

Judge: Mihara, J.

Court: California Court of Appeals Sixth Appellate District on appeal from the Superior Court, County of Santa Clara

Plaintiff's Attorney: Susan Brandt-Hawley

Defendant's Attorney: Margo Laskowska, Elisa Tanya Tolentino and Kathryn J. Zoglin

Description:

MoreLaw Receptionists
VOIP Phone and Virtual Receptionist Services

Call 918-582-6422 Today





Appellants Willow Glen Trestle Conservancy and Friends of the Willow Glen

Trestle (collectively the Conservancy) challenge the trial court’s denial of their mandate

petition. In 2014, respondent City of San Jose (the City) approved a project that included

the demolition of the Willow Glen Railroad Trestle (the project). The environmental

document for that approval was a mitigated negative declaration (MND). The

Conservancy’s 2018 petition alleged that the City violated the California Environmental

Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.) in 2018 by failing to

provide supplemental environmental review of the project before the City sought and

obtained a new Streambed Alteration Agreement (SAA) from the California Department

of Fish and Wildlife (CDFW) after the City’s prior SAA for the project expired. The

superior court found that the City was not obligated to provide supplemental

environmental review because the City’s action in seeking and obtaining a new SAA was

not a “new discretionary approval for the project” under California Code of Regulations,

2

title 14, section 15162 (CEQA Guidelines section 15162).

1

We agree with the superior

court and affirm its order.

I. Background

We traced the history of this project in our opinion in Trestle I, supra, 2

Cal.App.5th 457. The Willow Glen Railroad Trestle (the Trestle) is a wooden railroad

bridge built in 1922. The City acquired ownership of the Trestle in 2011. In 2013, the

City proposed a project to demolish the Trestle and replace it with a new steel truss

pedestrian bridge that would serve as a link in the City’s Three Creeks Trail system. (Id.

at p. 461.) The City approved the project, adopted a mitigated negative declaration

(MND), and found that the Trestle was not a historical resource. (Id. at pp. 461-462.)

Litigation ensued concerning whether the City should have considered the Trestle

to be a historical resource. At that time, the Trestle was not listed in the California

Register of Historical Resources. Had it been so listed, the City would have been

statutorily mandated to consider the Trestle an historical resource. (Trestle I, supra, 2

Cal.App.5th at p. 466; Pub. Resources Code, § 21084.1.) The City ultimately prevailed

in that litigation.

In May 2017, the California State Historical Resources Commission approved the

listing of the Trestle in the California Register of Historical Resources, and the Trestle

was so listed. In October 2017, the Commission denied the City’s request for

redetermination of that decision.

In March 2018, the City submitted to CDFW a “Notification of Lake or Streambed

Alteration” in connection with the project. The City had submitted such a notification in

1 Chapter 3 of division 6 of this title is known as the CEQA Guidelines. The CEQA

Guidelines are given “‘great weight’ ” in interpreting CEQA. (Friends of Willow Glen

Trestle v. City of San Jose (2016) 2 Cal.App.5th 457, 460, fn. 2 (Trestle I).)

3

2014 and been issued an SAA by CDFW at that time, but the 2014 SAA had expired at

the end of 2017.2

In April 2018, CDFW notified the City that the City’s “Notification”

was incomplete. In July 2018, the City submitted to CDFW a “proposed Temporary

Creek Access and Diversion Plan” for the project. The purpose of this plan was to divert

Los Gatos Creek during the Trestle demolition and bridge construction activities.

In August 2018, CDFW sent a draft SAA to the City and proposed revisions to the

City’s diversion plan. The City agreed to CDFW’s proposals and signed the final SAA in

August 2018; CDFW signed the final SAA in October 2018. CDFW found that the

project would not have any significant impacts on fish or wildlife “with the measures

specified in the 2014 MND and the [SAA].” The final SAA permitted CDFW to amend

it “at any time during its term if CDFW determines the amendment is necessary to protect

an existing fish or wildlife resource.”

The Conservancy sought judicial intervention to forestall the City’s plan to

immediately proceed with demolition of the Trestle. The superior court temporarily

enjoined the City from proceeding, but it ultimately denied the Conservancy’s petition.

The court found that the City’s actions in connection with obtaining the 2018 SAA were

not a discretionary approval for the project that required supplemental environmental

review. The court reasoned that the City’s approval of the MND in 2014 included

approval of the SAA and that the acts by the City involved in obtaining the new SAA did

not involve any “new discretionary approval” by the City. The Conservancy timely filed

a notice of appeal from the court’s order and sought a writ of supersedeas from this court

to forestall the destruction of the Trestle pending resolution of this appeal. We granted

writ relief to avoid demolition of the Trestle mooting this appeal.

2 An SAA has a maximum term of five years and may be extended only once and

not for more than five years. (Fish & G. Code, § 1605, subd. (a).)

4

II. Discussion

The Conservancy’s petition alleged that the City violated CEQA by “entering into

the discretionary [SAA] that is the final discretionary approval required prior to moving

forward with the demolition of [the Trestle].” It argued that supplemental environmental

review was required under Public Resources Code section 21166 before the City could

accept the SAA.

Public Resources Code section 21166 provides: “[N]o subsequent or

supplemental environmental impact report shall be required by the lead agency or by any

responsible agency, unless one or more of the following events occurs: [¶] . . . [¶]

(b) Substantial changes occur with respect to the circumstances under which the project

is being undertaken which will require major revisions in the environmental impact

report. [¶] (c) New information, which was not known and could not have been known

at the time the environmental impact report was certified as complete, becomes

available.” (Pub. Resources Code, § 21166.) This statute does not itself extend to a

project, such as this one, for which the supporting environmental document was an MND,

rather than an environmental impact report (EIR). (Friends of College of San Mateo

Gardens v. San Mateo County Community College Dist. (2016) 1 Cal.5th 937, 945 (San

Mateo Gardens).

CEQA Guidelines section 15162 extends Public Resources Code section 21166’s

framework to the situation where the environmental document for the project is an MND,

rather than an EIR. (San Mateo Gardens, supra, 1 Cal.5th at p. 956.) “Once a project

has been approved, the lead agency’s role in project approval is completed, unless further

discretionary approval on that project is required. Information appearing after an

approval does not require reopening of that approval. If after the project is approved,

any of the conditions described in subdivision (a) [(which mirror the circumstances set

forth in Public Resources Code section 21166)] occurs, a subsequent EIR or negative

declaration shall only be prepared by the public agency which grants the next

5

discretionary approval for the project, if any. In this situation no other responsible

agency shall grant an approval for the project until the subsequent EIR has been certified

or subsequent negative declaration adopted.” (CEQA Guidelines, § 15162(c), italics

added.)

CEQA Guidelines section 15162(c) applies only when, after the original approval

of a project, a “further discretionary approval on that project” is required. The

Conservancy argues that the City’s submission of a notification to CDFW in order to

obtain a new SAA after the prior SAA expired and acceptance of the new SAA amounted

to an “approval on that project” by the City. While it is true that CDFW’s issuance of the

final SAA was an “approval,” that action was not an approval by the City.

3

And, as the

Conservancy concedes, CDFW could not consider whether the Trestle was an historical

resource because CDFW’s environmental review was limited to fish and wildlife

resources. (Fish & G. Code, §§ 1602, 1603.) The Conservancy’s argument depends on

its characterization of the City’s actions in seeking and obtaining the SAA as an

“approval.”

An SAA was required for the project because the City was barred from diverting

or obstructing Los Gatos Creek without complying with Fish and Game Code sections

1602 and 1603. (Fish & G. Code, § 1602, subd. (a).) The first requirement was that a

detailed “notification” be sent by the City to CDFW. The second requirement fell on

CDFW: it had to ensure that the City’s notification was complete and then determine

whether the project may adversely affect a fish or wildlife resource. The third

requirement also burdened CDFW. If the activity might adversely affect a fish or

wildlife resource, CDFW was required to provide a draft SAA to the City that described

the impacted resource and included “reasonable measures necessary to protect the

3 It is undisputed in this case that “CDFW’s authority over the Project as a CEQA

responsible agency [was] limited to issuance of a streambed alteration agreement.”

6

resource.” (Fish & G. Code, §§ 1602, subd. (a), 1603.) The fourth requirement involved

the City. The City could either accept the draft SAA or notify CDFW of any

unacceptable measures. The final step was the resolution of any disagreements about

these measures by means of a statutorily prescribed process that could involve the

submission of disputes to arbitration. (Fish & G. Code, §§ 1602, 1603.)

The Conservancy claims that the City’s act of seeking and accepting the SAA was

a “discretionary approval on [the] project” under CEQA Guidelines section 15162(c) that

justified supplemental environmental review. This claim cannot withstand scrutiny

because it attempts to equate any action in connection with a project with an “approval

on” or an “approval for” the project.4

(Italics added.) If every action had to be

considered an “approval,” each and every step that the City took toward implementing an

approved project would necessarily constitute another “approval on” the project, thereby

endlessly reopening the City’s long-final consideration of the project’s environmental

impacts. Yet CEQA Guidelines section 15162 explicitly provides that “[i]nformation

appearing after an approval does not require reopening of that approval.” “Once a project

has been subject to environmental review and received approval, section 21166 and

CEQA Guidelines section 15162 limit the circumstances under which a subsequent or

supplemental EIR must be prepared. These limitations are designed to balance CEQA’s

central purpose of promoting consideration of the environmental consequences of public

decisions with interests in finality and efficiency.” (San Mateo Gardens, supra, 1 Cal.5th

at p. 949, italics added.) “In this context, ‘the interests of finality are favored over the

policy of encouraging public comment.’ [Citation.]” (Chaparral Greens v. City of Chula

4 The Conservancy attaches significance to CEQA Guidelines section 15162(c)’s

use of the word “on” rather than “of.” We see no significance. CEQA Guidelines section

15162(c) uses the term “for” interchangeably with “on,” and we see no justification for

assuming that a different meaning was intended to attach to an approval “for” a project as

opposed to an approval “of” a project.

7

Vista (1996) 50 Cal.App.4th 1134, 1150-1151.) The City’s post-approval actions

implementing the project did not constitute an “approval” within the meaning of CEQA

Guidelines section 15162(c).

The Conservancy maintains that different rules should apply to “a city’s own

project” than would apply to a “private project” because “[a]n agency always retains

authority to change course in implementing its own project.” In the Conservancy’s view,

because the City “retain[ed] discretion to reconsider or alter” the project, the City’s

failure to abandon the project was itself a new “discretionary approval for the project.”

While an agency may retain the discretion to abandon its own project, nothing in Public

Resources Code section 21166 or CEQA Guidelines section 15162 suggests that an

agency’s post-approval choice not to abandon its project itself constitutes an “approval

for the project” that justifies further environmental review. The purpose of CEQA

Guidelines section 15162 is to limit subsequent environmental review after finality of the

original environmental review, and the language of that section makes no distinction

between public and private projects. We reject the Conservancy’s attempt to expand the

reach of CEQA Guidelines section 15162 in contravention of that section’s purpose.

Now that we have laid these contentions to rest, it can be clearly seen that there is

no substance to the Conservancy’s claim that “[t]he SAA is a ‘further discretionary

approval’ made by the city as the lead agency for the [project] . . . .” The City’s actions

in connection with the SAA simply cannot be construed as an “approval for the project.”

The City’s 2018 application for an SAA (the “notification”) was not an “approval for the

project” because this notification was not an “approval.” The 2013 MND provided:

“The City will apply for a Streambed Alteration Agreement from CDFW and will be

responsible for the implementation of all its conditions.” When the City submitted a new

notification to CDFW in 2018 due to the expiration of the prior SAA, it was simply

implementing the project that it had already approved in 2014. The same is true as to the

City’s acceptance of the SAA, which was not an “approval” for the project but simply

8

another step in the implementation of the already approved project. The only new

“approval” was CDFW’s, and the Conservancy does not challenge CDFW’s decision to

approve the SAA.

As there was no further approval of the project in 2018, CEQA Guidelines section

15162(c) did not require supplemental environmental review. Consequently, the superior

court did not err in denying the Conservancy’s petition.
Outcome:
The superior court’s order is affirmed. The writ of supersedeas shall dissolve

upon the finality of this opinion.
Plaintiff's Experts:
Defendant's Experts:
Comments:

About This Case

What was the outcome of Willow Glen Trestle Conservancy v. City of San Jose?

The outcome was: The superior court’s order is affirmed. The writ of supersedeas shall dissolve upon the finality of this opinion.

Which court heard Willow Glen Trestle Conservancy v. City of San Jose?

This case was heard in California Court of Appeals Sixth Appellate District on appeal from the Superior Court, County of Santa Clara, CA. The presiding judge was Mihara, J..

Who were the attorneys in Willow Glen Trestle Conservancy v. City of San Jose?

Plaintiff's attorney: Susan Brandt-Hawley. Defendant's attorney: Margo Laskowska, Elisa Tanya Tolentino and Kathryn J. Zoglin.

When was Willow Glen Trestle Conservancy v. City of San Jose decided?

This case was decided on May 21, 2020.