Rochester City Lines, Co. vs. City of Rochester et al.
Date: 08-19-2015
Case Number: A13-1477
Judge: Justice David R. Stras
Court: STATE OF MINNESOTA IN SUPREME COURT
Plaintiff's Attorney: Gary A. Van Cleve and Rob A. Stefonowicz
Defendant's Attorney: Steven A. Diaz
a contractor to run its municipal bus service. The first question requires us to determine
the appropriate standard of review for an award of a government contract through a “best
value” bidding process, a method by which a government contractor is selected by
weighing various quantitative and qualitative factors. The second question is whether the
district court properly granted summary judgment to the City of Rochester on appellant
Rochester City Lines’s claims of unfair bias and favoritism in awarding the contract to
another bidder. Because we conclude that the district court properly granted summary
judgment on each of Rochester City Lines’s claims, except the general claim that the City
of Rochester acted unreasonably, arbitrarily, or capriciously in awarding the contract to
another party, we affirm in part, reverse in part, and remand to the district court for
further proceedings consistent with this opinion.
I.
For more than 30 years, Rochester City Lines, Co. (“RCL”) operated the
municipal bus service in Rochester. Although the City of Rochester (“City”) owns the
buses, bus-stop shelters, and other equipment, it contracted with RCL to operate the bus
service through a series of annual contracts. The City subsidized the operation through
the receipt of state and federal grants.
In 2011, the Federal Transit Administration (“FTA”) sent the City a series of
letters in which it informed the City that, in order to comply with federal procurement
4
requirements and continue to receive federal funding, the City needed to initiate a
competitive bidding process for its next contract. The City, which was receiving
approximately $1.6 million annually in FTA funding, complied with the FTA’s direction
and issued a Request for Proposals (“RFP”) in December 2011. Following the
methodology of the FTA’s guidance documents, the RFP stated that the City would use a
“best value” bidding process to select the proposal that presented “the highest quality of
service that best matche[d] the City’s requirements,” based on a set of predetermined
criteria. RCL filed a formal “bid protest” in an attempt to stop the bidding process,
claiming that the City’s actions were an unconstitutional taking of RCL’s property. The
bid protest failed, and RCL filed a lawsuit against the City.
RCL again unsuccessfully attempted to stop the bidding process, this time by
filing a motion for a temporary injunction with the district court. The competitive
bidding process continued, and the City received responsive bids from RCL and three
other companies. An evaluation committee, consisting of four City employees and four
outside reviewers, determined that the bid submitted by First Transit, Inc., a national bus
transportation company, presented the best value for the City. The Rochester City
Council followed the committee’s recommendation and awarded the contract to First
Transit on April 2, 2012.
After the City finalized its selection of First Transit, RCL filed another formal bid
protest. The City Attorney, acting under the terms of the RFP, denied RCL’s protest, and
the City Council affirmed his decision. RCL subsequently amended its complaint to add
claims against the City, members of the City Council, and First Transit, including a claim
5
seeking a declaration that the bidding process was unlawful. RCL also sued a member of
the City Council for defamation. In the meantime, First Transit began operating
Rochester’s municipal bus service on July 2, 2012. Unable to compete with a federally
subsidized operation, RCL ended its fixed-route service in Rochester the following day.
In November 2012, the district court granted summary judgment to the
respondents, including the City, on each of RCL’s claims. The court of appeals affirmed.
Rochester City Lines, Co. v. City of Rochester, 846 N.W.2d 444 (Minn. App. 2014). We
granted RCL’s petition for review to resolve two issues: (1) the applicable standard of
review of a “best value” competitive bidding process; and (2) whether the district court
erred when it granted summary judgment to the City on RCL’s bid-protest claims. We
denied review of all other issues decided by the court of appeals.1
II.
The first question presented in this case requires us to identify the standard of
review applicable to a best-value bidding process used by a municipality or other political
subdivision of the state. Best-value bidding, as described by the FTA, is a procedure by
which the award of a government contract depends on “which proposal represents the
‘best value’ [based] on an analysis of the tradeoff of qualitative technical factors and
price or cost factors.” U.S. Dep’t of Transp., Third-Party Contracting Guidance, FTA
Circular 4220.1F, VI-10 (Nov. 1, 2008, rev. Mar. 18, 2013) (hereinafter “FTA
Guidance”); see also Sayer v. Minn. Dep’t of Transp., 790 N.W.2d 151, 156 (Minn. 1 We denied review of RCL’s takings, inverse condemnation, defamation, due process, 42 U.S.C. §§ 1983 and 1988 (2012), and 49 U.S.C. § 5323 (2012) claims.
6
2010) (recognizing that the “best-value process differs from the lowest responsible bid
process in that it allows public agencies to consider factors other than cost when
awarding contracts”). Here, in accordance with the FTA Guidance, the City adopted
best-value bidding in its RFP and described it as
a selection process in which proposals contain both price and qualitative components, and award is based upon a combination of price and qualitative considerations. Qualitative considerations may include technical design, technical approach, quality of proposed personnel, and/or management plan. The award selection is based upon consideration of a combination of technical and price factors to determine (or derive) the offer deemed most advantageous and of the greatest value to the procuring agency.
Before the Legislature authorized best-value bidding for public construction
projects in 2007, the dominant procedure in Minnesota for government procurement was
the lowest-responsible-bidder process.2 Although public entities rarely used the best
value process prior to 2007, our cases have never distinguished between the various
methods of bidding when discussing the basic principles that guide our review of cases
involving government contracts. To the contrary, “[i]rrespective of what lawful method
is adopted or used in the letting of public contracts, it is for the courts to determine
whether officials in the exercise of their discretion have applied the method used in an
2 The lowest-responsible-bidder process requires a public agency to release the design and specifications for a government contract in advance of bidding. See Sayer, 790 N.W.2d at 155-56. Once the period for submitting a bid expires, the agency eliminates all non-conforming bids that “have a material variation from the given specifications.” Id. at 156. Of the remaining bids, the agency must award the contract to the qualifying bidder that offers to complete the contract at the lowest price. Id.
7
arbitrary, capricious, or unreasonable manner.” Griswold v. Ramsey Cty., 242 Minn. 529,
535, 65 N.W.2d 647, 651-52 (1954).
In Griswold, the Ramsey County Board allocated money for construction of a
county jail and released design specifications in advance of the bidding. See id. at 531,
65 N.W.2d at 649. Because all of the submitted bids exceeded the amount of money
allocated for the jail, however, the Board asked each bidder to subtract from its basic bid
the cost of certain items contained in the construction specifications. See id. These
alternative bids allowed the County to proceed with part of the construction and then
finish the remainder of the jail once funds became available. See id. at 531-32, 65
N.W.2d at 650. As it turned out, the County was able to find additional funds for the jail
prior to the construction, and it allocated those funds toward the completion of some of
the items listed in the winning bidder’s alternative bid. See id. at 532, 65 N.W.2d at 650.
Two taxpayers sued the County, arguing that the bidding process adopted by the
County was unlawful. See id. at 532, 65 N.W.2d at 650. In addressing the procedures
adopted by the County, we noted that no statute required the Board to adopt a
competitive-bidding process because, based on Ramsey County’s population, the
applicable statutes required competitive bidding only for the procurement of goods,
materials, and supplies, not for the construction of public buildings. See id. at 533, 65
N.W.2d at 650. Nevertheless, even in the absence of a statutory mandate, we held that
once the County adopted a lawful method for selecting a contractor, it had to give “all
contractors an equal opportunity to bid” and not pursue its chosen method “in an
unreasonable, arbitrary, or capricious manner.” Id. at 535, 65 N.W.2d at 652. We then
8
concluded that the alternative-bidding process that the Board adopted was unreasonable,
arbitrary, and capricious because it allowed bidders to make material changes to their
bids after the bidding had closed. See id. at 536, 65 N.W.2d at 652.
Griswold stands for the proposition that, in the absence of a statutory standard and
regardless of the method of bidding selected by a public agency, “it is for the courts to
determine whether officials in the exercise of their discretion have applied the method
used in an arbitrary, capricious, or unreasonable manner” upon receiving a proper
challenge. Id. at 535, 65 N.W.2d at 651-52; see also Tel. Assocs., Inc. v. Saint Louis Cty.
Bd., 350 N.W.2d 398, 400 (Minn. App. 1984) (applying the unreasonable, arbitrary, and
capricious standard to a best-value bidding process), aff’d, 364 N.W.2d 378, 381-82
(Minn. 1985). In this case, as in Griswold, there is no statute that required the City to
award the municipal-bus-service contract based on any specified bidding process, nor is
there any statute that addresses our standard of review. The contract is exempt from the
Uniform Municipal Contracting Law, Minn. Stat. § 471.345, subd. 2 (2014), because it
does not fall within the statute’s definition of “contract.” See Hubbard Broad., Inc. v.
Metro. Sports Facilities Comm’n, 381 N.W.2d 842, 846-47 (Minn. 1986). The
Minnesota Administrative Procedure Act is also inapplicable because municipalities are
not included within its scope. See Minn. Stat. § 14.02, subd. 2 (2014) (defining “agency”
to include only those entities with statewide jurisdiction). Accordingly, in the absence of
a statutory standard, Griswold provides the standard of review for best-value-bidding
processes.
9
The primary disagreement among the parties is the level of scrutiny required by
Griswold. RCL interprets Griswold as requiring courts to exercise robust judicial review
to invalidate any excessive exercise of discretion by a public agency, even in best-value
bidding. The City and First Transit, in contrast, argue that Griswold requires courts to
defer to value judgments made in weighing the subjective factors in best-value bidding,
such that only “significant errors” that draw into doubt the overall fairness of the process
and the good faith of the public agency would warrant intervention by a court. The court
of appeals announced yet a third approach, largely disconnected from Griswold, that
adopted what it referred to as “principles of common-law competitive-bidding,” but only
when those principles are consistent with best-value bidding processes. Rochester City
Lines, 846 N.W.2d at 455. Neither the parties nor the court of appeals accurately
describes our standard of review.
We have long applied the standard of review identified in Griswold to judicial
review of various agency actions, including actions taken by municipalities and other
political subdivisions. See, e.g., Carl Bolander & Sons v. City of Minneapolis, 502
N.W.2d 203, 207 (Minn. 1993) (applying the unreasonable, arbitrary, or capricious
standard of review to a city’s decision to require an Environmental Assessment
Worksheet before approving a project). In general terms, we have described an agency
action as arbitrary and capricious if it represented an exercise of the agency’s “will”
rather than its “judgment.” Markwardt v. State Water Res. Bd., 254 N.W.2d 371, 374
(Minn. 1977). Although we have explained that the unreasonable, arbitrary, and
capricious standard is “nonintrusive,” Dietz v. Dodge Cty., 487 N.W.2d 237, 239 (Minn.
10
1992), Griswold says that any procedure that “emasculates the safeguards of competitive
bidding” invalidates the process and the contract, 242 Minn. at 536, 65 N.W.2d at 652.
The essential safeguard of competitive bidding is, as we stated in Griswold, to “limit the
discretion of contract-making officials” to prevent “such abuses as fraud, favoritism,
improvidence and extravagance.” Id. The standard, in other words, requires courts to
examine the bidding procedures to ensure that they provide a fair process and incorporate
sufficient controls to safeguard against abuses, see Griswold, 242 Minn. at 536, 65
N.W.2d at 652, but it does not allow courts to substitute their judgments for those of
public officials, Vill. of Edina v. Joseph, 264 Minn. 84, 93, 119 N.W.2d 809, 815 (1962).
In the area of government contracts, federal courts have developed standards to
guide the exercise of judicial review over procurement decisions by federal agencies.
See, e.g., PAI Corp. v. United States, 614 F.3d 1347, 1351 (Fed. Cir. 2010). The federal
standards ensure that a government agency acts in good faith, not as a pretense “to let the
contract to some favored bidder,” and selects the bid that is “most advantageous to the
Government.” Heyer Prods. Co. v. United States, 140 F. Supp. 409, 414 (Ct. Cl. 1956).
In conducting a review of competitive-bidding processes, federal courts look to the
following factors to determine whether a government agency’s actions were arbitrary and
capricious:
subjective bad faith on the part of the officials; the absence of a reasonable basis for the administrative decision; the amount of discretion entrusted to the procurement officials by applicable statutes and regulations; and proven violation of pertinent statutes or regulations.
11
Prineville Sawmill Co. v. United States, 859 F.2d 905, 911 (Fed. Cir. 1988). Not all of
the factors need to be present to establish arbitrary and capricious behavior by a
government agency, and the application of the factors depends on the facts of each case.
Id. Because the federal standards have the same basic objectives of eliminating
favoritism and fraud in procurement decisions and ensuring the good-faith conduct of
government officials in securing government contracts, they are instructive in
determining whether the acts of a municipality or other political subdivision are
unreasonable, arbitrary, or capricious under Griswold.
Accordingly, we hold that the unreasonable, arbitrary, or capricious standard
adopted in Griswold is the appropriate standard for reviewing a city’s or county’s
decision to award a government contract after a “best value” bidding process.
III.
The second question in this case requires us to determine, based on Griswold and
the evidence presented to the district court at the summary-judgment stage, whether the
district court erred when it granted summary judgment to the City and First Transit. As
relevant here, the district court found that various irregularities during the bidding
process did not rise to the level of arbitrary or capricious behavior by the City. It
therefore concluded that, even after drawing all inferences in RCL’s favor, there were no
genuine issues of material fact for trial. In affirming the district court’s grant of summary
judgment, the court of appeals reached the same conclusion. Rochester City Lines, 846
N.W.2d at 462.
12
We review a district court’s grant of summary judgment de novo to determine
(1) whether there are any genuine issues of material fact, and (2) whether the district
court correctly applied the law. Mattson Ridge, LLC v. Clear Rock Title, LLP, 824
N.W.2d 622, 627 (Minn. 2012). A fact is material “if its resolution will affect the
outcome of a case.” O’Malley v. Ulland Bros., 549 N.W.2d 889, 892 (Minn. 1996). At
the summary-judgment stage, we view the evidence in the light most favorable to the
nonmoving party—here, RCL—and resolve all doubts and factual inferences against the
moving parties—here, the City and First Transit. Nord v. Herreid, 305 N.W.2d 337, 339
(Minn. 1981).
We can sort RCL’s claims into four general categories. The first two include
challenges to the terms of the RFP and the procedures undertaken by the City in
addressing the bid protest. RCL’s third claim alleges that an “organizational conflict of
interest” on the part of First Transit, the winning bidder, contaminated the entire process.
RCL’s final claim is that the cumulative irregularities in the bidding process rendered the
City’s actions arbitrary, capricious, or unreasonable. We address each of RCL’s
arguments in turn.
A.
RCL’s first claim relates to the terms of the RFP, which it characterizes as
“excessive.” Specifically, RCL argues that the requirements for cash reserves were
“unreasonable” and that the company’s successful operations made it unnecessary and
unfair for it, as the incumbent contractor, to have to obtain outside references.
13
Regardless of the merits of RCL’s argument, it has forfeited this claim by failing
to raise it in accordance with the pre-bid protest procedures outlined in the RFP.
According to the RFP, “[p]rotests regarding any aspect of the RFP document, attached
materials, and [the City’s] selection procedures must be submitted in writing prior to the
proposal opening date and time.” RCL submitted a pre-bid protest, but as RCL concedes,
its protest was limited to the claim that opening the contract for public bidding
constituted an unconstitutional taking of its property. Nowhere in the documents
submitted to the City prior to the bidding did RCL object to any of the contractor
qualifications as unreasonable or excessive. Indeed, once the City denied RCL’s pre-bid
protest, RCL submitted a responsive bid to the City. As a federal district court in
Minnesota recently observed, “[c]ontractors ‘cannot sit on their rights to challenge what
they believe is an unfair solicitation, roll the dice and see if they receive an award and
then, if unsuccessful, claim the solicitation was infirm.’ ” C.S. McCrossan Constr., Inc.
v. Minn. Dep’t of Transp., 946 F. Supp. 2d 851, 862 n.17 (D. Minn. 2013) (quoting Blue
& Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1314 (Fed. Cir. 2007)). Accordingly,
by failing to use the administrative procedure provided by the City, RCL forfeited its
challenge to the terms of the RFP.
B.
RCL’s second claim alleges that the City Attorney, the individual who made the
initial determination to deny RCL’s bid-protest filings, was biased. The source of the
City Attorney’s bias, according to RCL, is that, by advising and counseling the City on
the RFP and the bidding process, the City Attorney had an inherent conflict of interest
14
that disqualified him from making a decision, preliminary or otherwise, on RCL’s bid
protests.
RCL characterizes the City’s denials of its bid-protest filings as quasi-judicial
decisions. However, rather than seeking a writ of certiorari from the City’s decisions in
the court of appeals, as required by statute, RCL instead filed an action in Olmsted
County District Court. See Minn. Stat. § 606.01 (2014). To the extent that RCL
challenges the City’s quasi-judicial decisions in the current action, those challenges were
never properly before the district court because such decisions are reviewable only by
writ of certiorari in the court of appeals. See Cty. of Washington v. City of Oak Park
Heights, 818 N.W.2d 533, 539 (Minn. 2012). We agree with RCL that the City’s bid
protest denials were quasi-judicial decisions.
Broadly speaking, we have described legislative acts as those that affect the rights
of the public generally, whereas quasi-judicial acts are those that affect the rights of just a
few individuals. Id. We have recognized that quasi-judicial decisions share three
characteristics: (1) an investigation into a disputed claim and the weighing of evidentiary
facts; (2) the application of those facts to a prescribed standard; and (3) a binding
decision regarding a disputed claim. Id. at 540.
As RCL acknowledges, the City investigated RCL’s claims and weighed the facts
under the standards contained in the RFP, the FTA Circular, and various federal statutes.
For example, the City rejected some of RCL’s claims, including the claim of bias by the
City Attorney, based on section 5.1.2 of the RFP, which required bidders to challenge the
terms of the RFP in a pre-bid protest. After considering the facts in light of the RFP, the
15
FTA Circular, and federal-contracting statutes, the City issued a binding decision
rejecting RCL’s claims. The presence of each of the three characteristics of a quasi
judicial decision means that the City’s bid-protest denials were reviewable only by writ
of certiorari in the court of appeals. Id. at 539; Handicraft Block Ltd. P’ship v. City of
Minneapolis, 611 N.W.2d 16, 24 (Minn. 2000) (holding that a decision by a city with all
three characteristics of a quasi-judicial decision was reviewable only by the court of
appeals). Accordingly, because RCL’s second claim challenges the City’s quasi-judicial
decisions, the district court lacked subject matter jurisdiction to consider it.
C.
RCL’s third claim alleges that First Transit, the winning bidder, had an
“organizational conflict of interest” that rendered the entire process void. Under federal
law, an organizational conflict of interest exists when, “because of other activities or
relationships with other persons, a person is unable or potentially unable to render
impartial assistance or advice to the Government, or the person’s objectivity in
performing the contract work is or might be otherwise impaired, or a person has an unfair
competitive advantage.” 48 C.F.R. § 2.101 (2014). The FTA Guidance, which the City
incorporated by reference in the RFP, states that an organizational conflict of interest can
arise when a bidding contractor: (1) is unable to provide impartial or objective assistance
to the agency; (2) has unequal access to nonpublic information; or (3) has been allowed
to establish biased ground rules. See FTA Guidance, supra, at VI-5. The FTA Guidance
required the City to identify and evaluate potential organizational conflicts of interest,
and to take steps to avoid or mitigate them. FTA Guidance, supra, at VI-5-VI-6.
16
The basis for RCL’s claim that an inadequately mitigated organizational conflict
of interest existed is a conversation in which a City employee told First Transit’s general
manager that RCL’s operations manager, Randy Huston, was “someone who [the City]
like[d] . . . [,] someone who kn[ew] the operation.” RCL argues that the City gave First
Transit an “unfair competitive advantage” by revealing proprietary information.
To establish an organizational conflict of interest under the second category of the
FTA Guidance, a contractor must show not only that another contractor “has an unfair
competitive advantage,” but also that the contractor gained such an advantage “through
obtaining access to nonpublic information during the performance of an earlier contract.”
FTA Guidance, supra, at VI-5; see Jacobs Tech. Inc. v. United States, 100 Fed. Cl. 198,
210 (2011). Here, it is undisputed that First Transit has never had, much less performed,
another contract with the City, so RCL’s unequal-access claim cannot give rise to an
organizational conflict of interest.
First Transit also did not have impaired objectivity, because there is no evidence
that it assisted the City in evaluating itself or its competitors. Vantage Assocs., Inc. v.
United States, 59 Fed. Cl. 1, 10 (2003). Nor did First Transit create biased ground rules,
because it did not assist the City in setting the terms of the RFP. Id. Moreover, even if
there were evidence of a conflict, there is certainly nothing to indicate that such a conflict
was “so pervasive” that it would require the invalidation of the entire bidding process.
See PAI Corp v. United States, 614 F.3d 1347, 1351 (Fed. Cir. 2010). In sum, nothing in
the record shows, either directly or by implication, that First Transit’s activities or
relationships resulted in an organizational conflict of interest.
17
D.
RCL’s final, “catch all” claim is that numerous irregularities in the bidding
process suggest that the City’s decision to award the bus-service contract to First Transit
was arbitrary, capricious, or unreasonable under Griswold.3 Because the district court
granted summary judgment to the City and First Transit on RCL’s claims, the question
before us is not whether RCL will eventually prevail at trial, but whether genuine issues
of material fact exist and the district court correctly applied the Griswold standard. DLH,
Inc. v. Russ, 566 N.W.2d 60, 70 (Minn. 1997) (“The district court’s function on a motion
for summary judgment is not to decide issues of fact, but solely to determine whether
genuine factual issues exist.”).
Based on Griswold, we must determine whether the evidence regarding alleged
procedural irregularities, viewed in the light most favorable to RCL, would permit a fact
finder to reasonably conclude that the City’s decision to award the contract to First
Transit was arbitrary, capricious, or unreasonable. See 242 Minn. at 535, 65 N.W.2d at
652. For at least two reasons, RCL has presented sufficient evidence to create a genuine
issue of material fact on the question of whether the City awarded the contract to First
Transit based on an unfair and biased process.
First, the record contains evidence that the interview process involved
inconsistencies that might demonstrate favoritism toward First Transit. When First 3 In contrast to the City’s decision to deny RCL’s bid protests, the City’s decision to award the contract to First Transit was not a quasi-judicial decision, because the bidding process did not involve the resolution of a “disputed claim.” See City of Oak Park Heights, 818 N.W.2d at 540.
18
Transit submitted its bid, it listed two of RCL’s managers as among the personnel who
would manage the bus system if it received the contract from the City. First Transit’s bid
appears to have been consistent with the City’s requirement that each of the bidders make
a good-faith effort to hire RCL employees if selected. However, as part of the selection
process, the City also asked bidders to have their key managers attend an interview with
the City’s evaluation committee. First Transit was the only bidder among the four that
received permission from the City to substitute other employees for the managers it listed
in its bid to represent it at the interview with the committee. Then, rather than basing its
interview scores only on the personnel who actually attended the interview on behalf of
each bidder, the committee awarded points to both RCL and First Transit based on the
performance of the two RCL managers during RCL’s interview. The City never
informed the other bidders that it had allowed First Transit to list RCL’s managers in its
bid, to bring substitute personnel to its interview, or that it had awarded points to First
Transit based on the performance of RCL’s managers during RCL’s interview. Based on
this evidence, RCL argues that the City violated the terms of the RFP and showed
favoritism toward First Transit.
Second, RCL produced evidence that two employees of the City who had initially
agreed to serve as references for RCL later refused to do so based on advice from the
City. Specifically, RCL relied on evidence, obtained during discovery, that the City
Attorney advised these two employees not to serve as references because it would
interfere with their duties on the evaluation committee. However, despite deciding that
they would no longer serve as references based on the City Attorney’s advice, neither
19
employee informed RCL of the decision to withdraw as a reference, which reduced the
total number of points available to RCL on the past-performance criterion. As the district
court found, these actions “effectively left RCL in the lurch” and are “objectively subject
to criticism.”
Evidence of these two procedural irregularities raises the specter of pervasive bias
against RCL, even if, as the dissent argues, there are other legitimate explanations for the
City’s actions. At least at this stage of the case, the evidence in the record does not
exclude the possibility that bias against RCL, or favoritism toward First Transit,
improperly influenced the City’s bidding process. RCL is entitled to a trial on whether
the City made the award arbitrarily, capriciously, or unreasonably.
In granting summary judgment to the City and First Transit, the district court
improperly drew inferences against RCL and ignored contradictory evidence in the
record, both of which the district court may not do on summary judgment. We have
reiterated on numerous occasions that district courts are not permitted to weigh the
evidence in deciding a motion for summary judgment, see, e.g., DLH, 566 N.W.2d at 70,
and that any inferences must be drawn against, rather than in favor, of the moving party,
see J.E.B. v. Danks, 785 N.W.2d 741, 751 (Minn. 2010).
The dissent makes the same error as the district court by improperly drawing
inferences in favor of the City. Even if, as the dissent argues, the relevant facts were not
in dispute, the parties vigorously disagree about whether the procedural irregularities in
the record are indicative of pervasive bias by the City, or alternatively, whether they were
just inadvertent errors that had no relevance to the City’s bidding process. The point is
20
that reasonable minds can disagree about the inferences that may be drawn from the
record, and as we have repeatedly stated, “summary judgment is inappropriate when
reasonable [people] might draw different conclusions from the evidence presented.”
DLH, 566 N.W.2d at 69 & n.6 (collecting cases).4
Affirmed in part, reversed in part, and remanded.
About This Case
What was the outcome of Rochester City Lines, Co. vs. City of Rochester et al.?
The outcome was: For the foregoing reasons, we affirm the judgment of the court of appeals in part, reverse in part, and remand to the district court for further proceedings consistent with this opinion. Affirmed in part, reversed in part, and remanded.
Which court heard Rochester City Lines, Co. vs. City of Rochester et al.?
This case was heard in STATE OF MINNESOTA IN SUPREME COURT, MN. The presiding judge was Justice David R. Stras.
Who were the attorneys in Rochester City Lines, Co. vs. City of Rochester et al.?
Plaintiff's attorney: Gary A. Van Cleve and Rob A. Stefonowicz. Defendant's attorney: Steven A. Diaz.
When was Rochester City Lines, Co. vs. City of Rochester et al. decided?
This case was decided on August 19, 2015.