Please E-mail suggested additions, comments and/or corrections to Kent@MoreLaw.Com.
Help support the publication of case reports on MoreLaw
American Safety Casualty Insurance Company v. City of Olympia
Date: 12-27-2007
Case Number: 79001-9
Judge: Bobbe J. Bridge
Court: Supreme Court of Washington on appeal from the Thurston County Superior Court
Plaintiff's Attorney:
Thomas Harding Wolfendale
Kirkpatrick & Lockhart Preston Gates Ell
925 4th Ave Ste 2900
Seattle, WA, 98104-1158
Athan Emmanuel Tramountanas
Kirkpatrick & Lockhart Preston Gates Ell
925 4th Ave Ste 2900
Seattle, WA, 98104-1158
Paul J. Lawrence
Kirkpatrick & Lockhart Preston Gates Ell
925 4th Ave Ste 2900
Seattle, WA, 98104-1158
Amicus Curiae on behalf of Washington State School Construction Alliance
Richard Ottesen Prentke
Attorney at Law
1201 3rd Ave Ste 4800
Seattle, WA, 98101-3266
Graehm Christopher Wallace
Perkins Coie LLP
1201 3rd Ave Ste 4800
Seattle, WA, 98101-3099
Melissa Robertson
Perkins Coie LLP
1201 3rd Ave Ste 4800
Seattle, WA, 98101-3099
Andrew L Greene
Perkins Coie LLP
1201 3rd Ave Ste 4800
Seattle, WA, 98101-3266
Defendant's Attorney:
Jerret E. Sale
Bullivant Houser Bailey PC
1601 5th Ave Ste 2300
Seattle, WA, 98101-1618
Deborah Lynn Carstens
Bullivant Houser Bailey PC
1601 5th Ave Ste 2300
Seattle, WA, 98101-1618
Amicus Curiae on behalf of Washington State Assoc of Municipal Attorneys
Daniel Brian Heid
City of Auburn
25 W Main St
Auburn, WA, 98001-4998
Amicus Curiae on behalf of Association of Washington Cities
Daniel Brian Heid
City of Auburn
25 W Main St
Auburn, WA, 98001-4998
This case arises from a contract dispute between American
Safety Casualty Insurance Company (American Safety)1 and the city of Olympia
(City) and the trial court's award of summary judgment in favor of the City.2 There
is no dispute that American Safety did not follow the contract's provisions when it
sought additional compensation for work it had performed and that it filed suit after
the 180-day time limit established in the contract. However, American Safety
argues that the City implicitly waived its right to demand compliance with the
contract's provisions when it agreed to negotiate and try to reach a settlement.
American Safety argues that the trial court erred in granting summary judgment to
the City, and that the Court of Appeals was correct to reverse because an issue of
material fact existed as to whether the City waived its contractual defenses. The
City maintains that it expressly reserved its rights; that any waiver of rights must be
unequivocal; and that, at most, its acts were equivocal and thus did not constitute a
waiver. We agree with the City and reverse the Court of Appeals.
I
Facts and Procedural History
In 2000, the City awarded contractor Katspan, Inc. (Katspan) a contract to
construct a segment of the LOTT southern connection pipeline project. Under the
terms of the contract, the contractor was required to follow the contractual
procedures if it wished to file a protest, formal claim, or lawsuit.3 Katspan agreed
that protests to any change orders or compensation issues were to be brought to the
attention of the project engineer immediately. If Katspan disagreed with the project
engineer's resolution of the protest, it could file an administrative claim. Any cause
of action under the contract was to be brought within 180 days of the final
acceptance and closeout of the project. Pursuant to the contract, failing to follow
the procedures constituted a waiver of the claims. Clerk's Papers (CP) at 47 ("By
failing to follow the procedures of this section [Procedure and Protest by the
Contractor] and Section 1-09.11 [Disputes and Claims], the Contractor completely
waives any claims for protested work."); CP at 55 ("[T]he Contractor's failure to
bring suit within the [180-day] time period provided, shall be a complete bar to any
such claims or causes of action.").
From the beginning, the City was frustrated with Katspan's work -- the City
had to direct Katspan to fix deficient work, and Katspan failed to meet the
scheduling requirements. On April 2, 2001, the City sent Katspan a letter stating
that it considered Katspan to be in breach of the contract, as Katspan had not
completed the work according to the time frame established in the contract. The
City indicated that, pursuant to the contract, it was entitled to collect liquidated
damages from Katspan for the breach. The City also stated that it "reserve[d] its
right to demand strict compliance with all other terms of the contract documents,
including . . . the required procedure for protest by the Contractor." CP at 338. On
April 18, 2001, the City sent Katspan a letter in which the City stated that because
Katspan failed to follow the procedures set forth in the contract, it had waived its
claims. Katspan never disputed this letter.
When the work was finished, the City began the process of finally accepting
the project as complete. On May 10, 2001, the project engineer, Parametrix Inc.
(Parametrix), sent Katspan a letter asking Katspan to submit its final cost proposals
in order to close out the project. Katspan did not respond. On May 25, 2001,
Parametrix sent Katspan another letter, again asking for Katspan to provide the
information by June 4 so it could begin the closeout. Katspan responded on June
11, 2001, saying that it was "in the final stages of compiling data" and that the
requested information "should be ready shortly." CP at 95. Parametrix did not
receive the information, so it reviewed the files and changes to the original contract
and computed what it considered to be reasonable costs for the additional work. On
June 18, 2001, Parametrix sent Katspan a letter with the change order it prepared to
cover the additional work. Parametrix asked Katspan to sign the final payment
estimate and return it if it was acceptable. Katspan never responded, and on July 2,
2001, the City sent Katspan a letter stating that if Katspan did not return the final
payment request, the City would unilaterally establish final acceptance of the
project. The City received no response, and on September 10, 2001, the City
unilaterally closed out the project.
On November 26, 2001, American Safety, surety for Katspan,4 sent the City a
"Request for Equitable Adjustment on Southern Connection Pipeline Project"
(Request). CP at 116-321. The document did not comply with the standards set out
in the contract for filing a claim. American Safety received no response to the
Request until March 14, 2002 (more than 180 days after the final acceptance date),
when American Safety left a voicemail message for the City's counsel, stating that it
had some ideas for "some possible quick solutions." CP at 329.
The City agreed to enter negotiations, but asked American Safety to provide
further information so it could determine whether a quick resolution was possible.
American Safety subsequently sent the City two three-ring binders of documents;
however, it did not include all of the information that the City needed to evaluate the
request. On August 1, 2002, the City sent American Safety a letter in which it
asked for further documentation. American Safety indicated that it was having
trouble obtaining the requested information. On October 2, 2002, the City reiterated
that it was willing to negotiate, but that it would not do so unless American Safety
could provide adequate backup information for its claims. The City received no
response, and on November 12, 2002, sent American Safety a letter in which it
stated that "[w]ithout waiving any of its defenses, LOTT has stated several times
that it is willing to negotiate these claims in order to come to a quick resolution."
CP at 354. The City asked whether American Safety was still interested in
negotiations, as the City had received no response from its last request for
information.
On January 22, 2003, American Safety informed the City that it had received
four or five boxes of documents from Katspan for the City to review. Upon review,
the City discovered that some information was still missing. On April 23, 2003, the
City sent American Safety yet another letter requesting certain documentation. The
City stated that if it did not receive the requested information by May 16, 2003, it
would deny American Safety's claim. On May 14, 2003, American Safety wrote to
the City that although it believed it had provided sufficient information, "we are
presently determining the feasibility of accommodating LOTT's request for
supplemental cost information, or creating the equivalent." CP at 368. The
documentation never arrived, and on May 16, 2003, the City denied American
Safety's Request.
On July 31, 2003, Thomas Presnell, a claims consultant representing
American Safety, e-mailed Paul Pedersen, the City's forensic accountant, asking
him whether they could meet to discuss the project and the information the City
needed to complete its audit. Pedersen responded that he had been given the green
light to discuss the matter. Presnell and Pedersen exchanged a few more e-mails in
which they discussed what form the requested information should be in and when
they could meet. However, no meeting ever took place.
On May 21, 2004 -- more than a year after the City denied American Safety's
claim -- American Safety called the City and said that it had finally obtained the
information necessary for the City to evaluate its Request. The City responded that
the Request did not comply with the procedures set forth in the contract and that the
claim had been denied more than a year prior for lack of information.5
On August 17, 2004, American Safety filed suit against the City in Thurston
County Superior Court. The trial court granted summary judgment in favor of the
City, finding that American Safety did not comply with the contractual provisions
and that the City had not waived its right to demand compliance with these agreed
upon procedures. The Court of Appeals reversed, finding that whether the City had
waived its right to demand compliance with the contractual provisions was an issue
of material fact for a fact finder to decide. Am. Safety Cas. Ins. Co. v. City of
Olympia, 133 Wn. App. 649, 662, 137 P.3d 865 (2006). The City petitioned for
review in this court, which we accepted on June 8, 2007. Am. Safety Cas. Ins. Co.
v. City of Olympia, 160 Wn.2d 1017, 162 P.3d 1130 (2007). We must now decide
whether the trial court was correct in granting summary judgment or whether an
issue of material fact exists as to whether the City waived the contractual
provisions.
II
Analysis
We review an order of summary judgment de novo. Jones v. Allstate Ins.
Co., 146 Wn.2d 291, 300, 45 P.3d 1068 (2002). Summary judgment is proper "if
the pleadings, affidavits, and depositions establish that there is no genuine issue of
material fact and that the moving party is entitled to judgment as a matter of law."
Id. at 300-01.
The City argues that the Court of Appeals erred when it failed to recognize
that the rule of Mike M. Johnson, Inc. v. Spokane County, 150 Wn.2d 375, 78 P.3d
161 (2003), applies. In Mike M. Johnson, we considered whether Spokane county
implicitly waived its right to demand compliance with contractual procedures when
the county entered into negotiations with Mike M. Johnson, Inc. (MMJ) even after
MMJ did not follow the agreed upon procedures. Id. at 377-78. In that case, the
county and MMJ entered into a contract for MMJ to construct two sewer projects.
Id. at 378. Pursuant to the contract, which included the same standard
specifications as those at issue in the instant case, the county could revise the scope
of MMJ's work through a change order. Id. at 378-79. If MMJ objected to the
change order, the contact specified that it must file an immediate protest. Id. at 379.
Under the terms of the contract, failing to follow the contractual procedures would
result in waiver of the claims. Id. at 380.
During the course of the project the county submitted a change order, and
MMJ did not object. Id. at 378-79. MMJ later sent the county a letter addressing
seven points of concern, one of which was the change order. Id. at 380. The letter
indicated that MMJ had to perform additional work to accommodate the change
order, which was causing additional costs and delays. Id. at 380-81. The county
responded to MMJ by stating that if MMJ thought it had a claim for additional
compensation, it must follow the terms of the contract and submit a claim pursuant
to the contractual provisions. Id. at 381. Correspondence between MMJ and the
county continued, and the county stated that it was willing to discuss a settlement
and attempt to avoid litigation but that it did not intend to waive any of its
contractual defenses. Id. at 381-84. The parties were unable to resolve the dispute
out of court, and MMJ ultimately filed a complaint against the county for additional
compensation. Id. at 384. The trial court found that because MMJ failed to follow
the contractual procedures to pursue a claim for additional compensation, its claim
failed as a matter of law. Id. at 385. The Court of Appeals reversed, holding that
an issue of material fact existed regarding whether the county's conduct constituted
implied waiver. Mike M. Johnson, Inc. v. Spokane County, 112 Wn. App. 462,
471, 49 P.3d 916 (2002).
On appeal before this court, MMJ argued that a reasonable fact finder could
determine that the county's act of agreeing to enter into negotiations was evidence
of intent to waive the contractual procedures, and thus summary judgment was
improper. See Mike M. Johnson, 150 Wn.2d at 391. We disagreed. We held that,
absent waiver, failure to comply with contractual procedures bars relief and that
"waiver by conduct 'requires unequivocal acts of conduct evidencing an intent to
waive,'" Id. at 391 (emphasis added) (quoting Absher Constr. Co. v. Kent Sch.
Dist. No. 415, 77 Wn. App. 137, 143, 890 P.2d 1071 (1995)). By repeatedly stating
that it was not waiving its rights, the county clearly did not unequivocally waive
those rights and thus summary judgment in favor of the county was proper. Id. at
392.
In the instant case, the City asserted in correspondence that it reserved its
right to demand strict compliance with the contractual procedures and that it was
willing to negotiate "[w]ithout waiving any of its defenses." CP at 327, 338, 354.
American Safety points out, however, that the City expressly reserved its rights just
twice prior to the end of the project, and just once after the project's completion.
Appellant's Reply Br. at 5. In other correspondence, the City did not reference the
contractual provisions and evidenced a willingness to negotiate in order to avoid
litigation.6 According to American Safety, this distinguishes the case from Mike M.
Johnson, where the county "continuously" asserted its rights. Resp't's Suppl. Br. at
12 (emphasis omitted). The Court of Appeals agreed, finding that because "the City
referred to strict compliance with the contract terms in only three instances," the
City's actions were "equivocal" and thus a finder of fact must decide whether the
City implicitly waived its rights. Am. Safety, 133 Wn. App. at 659, 661 (emphasis
added).
The Court of Appeals misapplied the law. While in some cases equivocal
conduct does create an issue of material fact, in which case it would be improper to
grant summary judgment, such ambiguity here means that the conduct by definition
was not unequivocal, as is required for waiver: "[W]aiver by conduct 'requires
unequivocal acts of conduct evidencing an intent to waive,'" Mike M. Johnson, 150
Wn.2d at 391 (emphasis added) (quoting Absher, 77 Wn. App. at 143). At most,
the fact that the City agreed to consider negotiations -- and we point out that the City
never did enter into negotiations, for it never received the information it required as
a prerequisite to doing so -- constitutes equivocal conduct.7 Equivocal conduct by
definition cannot be unequivocal, and the Court of Appeals thus erred when it found
that "the equivocal nature of the City's conduct" warranted a trial on the merits.
Am. Safety, 133 Wn. App. at 661 (emphasis added). Given that the City three times
expressly asserted that it was not waiving its defenses, a reasonable juror could not
find that the City unequivocally did exactly the opposite. Amicus Washington
School Construction Alliance points out that "[t]he 'unequivocal acts' standard is
demanding for good reason. Waiver permanently surrenders an established
contractual right." Br. of Amicus Curiae Wash. State Sch. Constr. Alliance at 11
(emphasis added). Because American Safety admittedly did not comply with the
contractual provisions, and because the City did not unequivocally waive its right to
demand compliance with these provisions, we find that the trial court was correct in
granting summary judgment to the City.
American Safety also argues that Mike M. Johnson can be distinguished
because there, the county and MMJ were discussing seven different issues, only one
of which concerned the change order and whether MMJ followed the contractual
procedures. Therefore, according to American Safety, "continued negotiations of
the claim [in Mike M. Johnson] were insufficient to create a waiver because those
negotiations related several issues, not just the change order." Appellant's Opening
Br. at 29.
It is unclear why this distinction should result in a different outcome here. In
Mike M. Johnson we noted the fact that the county and MMJ were negotiating
several issues in order to point out that if we found that entering into negotiations
constituted an implicit waiver of contractual rights, then the county likely would
have had to stop all negotiations on all issues for fear of waiving the mandatory
claim provisions. 150 Wn.2d at 392. The same policy consideration is at issue
here. Were we to find that by entering into negotiations a party waives its
contractual rights, we would frustrate the negotiation and settlement process.
Washington law strongly favors the public policy of settlement over litigation. E.g.,
City of Seattle v. Blume, 134 Wn.2d 243, 258, 947 P.2d 223 (1997) ("[T]he express
public policy of this state . . . strongly encourages settlement."); Seafirst Ctr. Ltd.
P'ship v. Erickson, 127 Wn.2d 355, 366, 898 P.2d 299 (1995) (referring to
"Washington's strong public policy of encouraging settlements"); Haller v. Wallis,
89 Wn.2d 539, 545, 573 P.2d 1302 (1978) ("[T]he law favors amicable settlement
of disputes . . . ."). If we found that by agreeing to enter into negotiations the City
waived its rights under the contract, we would deter future parties from attempting
settlement before resorting to use of the courts. Such result would be directly
contrary to established public policy and thus we find that entering into settlement
negotiations, without anything more, does not constitute an implied waiver of
contractual defenses.
Attorney Fees
Because the City has prevailed here, it is entitled to reasonable attorney fees
and costs. RCW 39.04.240; RAP 18.1.
* * *
http://www.courts.wa.gov/opinions/index.cfm?fa=opinions.showOpinion&filename=790019MAJ
City's acts were, at most, equivocal. Agreeing to enter into negotiations, without
more, does not constitute an implied waiver of contractual rights. Therefore, since
American Safety admittedly did not comply with the contractual provisions and thus
waived its claim to additional compensation, the trial court was correct in granting
summary judgment to the City. The decision of the Court of Appeals is reversed.
About This Case
What was the outcome of American Safety Casualty Insurance Company v. City of Oly...?
The outcome was: Implied waiver of contractual rights requires unequivocal acts, and here the City's acts were, at most, equivocal. Agreeing to enter into negotiations, without more, does not constitute an implied waiver of contractual rights. Therefore, since American Safety admittedly did not comply with the contractual provisions and thus waived its claim to additional compensation, the trial court was correct in granting summary judgment to the City. The decision of the Court of Appeals is reversed.
Which court heard American Safety Casualty Insurance Company v. City of Oly...?
This case was heard in Supreme Court of Washington on appeal from the Thurston County Superior Court, WA. The presiding judge was Bobbe J. Bridge.
Who were the attorneys in American Safety Casualty Insurance Company v. City of Oly...?
Plaintiff's attorney: Thomas Harding Wolfendale Kirkpatrick & Lockhart Preston Gates Ell 925 4th Ave Ste 2900 Seattle, WA, 98104-1158 Athan Emmanuel Tramountanas Kirkpatrick & Lockhart Preston Gates Ell 925 4th Ave Ste 2900 Seattle, WA, 98104-1158 Paul J. Lawrence Kirkpatrick & Lockhart Preston Gates Ell 925 4th Ave Ste 2900 Seattle, WA, 98104-1158 Amicus Curiae on behalf of Washington State School Construction Alliance Richard Ottesen Prentke Attorney at Law 1201 3rd Ave Ste 4800 Seattle, WA, 98101-3266 Graehm Christopher Wallace Perkins Coie LLP 1201 3rd Ave Ste 4800 Seattle, WA, 98101-3099 Melissa Robertson Perkins Coie LLP 1201 3rd Ave Ste 4800 Seattle, WA, 98101-3099 Andrew L Greene Perkins Coie LLP 1201 3rd Ave Ste 4800 Seattle, WA, 98101-3266. Defendant's attorney: Jerret E. Sale Bullivant Houser Bailey PC 1601 5th Ave Ste 2300 Seattle, WA, 98101-1618 Deborah Lynn Carstens Bullivant Houser Bailey PC 1601 5th Ave Ste 2300 Seattle, WA, 98101-1618 Amicus Curiae on behalf of Washington State Assoc of Municipal Attorneys Daniel Brian Heid City of Auburn 25 W Main St Auburn, WA, 98001-4998 Amicus Curiae on behalf of Association of Washington Cities Daniel Brian Heid City of Auburn 25 W Main St Auburn, WA, 98001-4998.
When was American Safety Casualty Insurance Company v. City of Oly... decided?
This case was decided on December 27, 2007.